New York City closes tunnel supplying half of its water for big $2B fix

New York City is embarking on a critical $2 billion project to address massive leaks beneath the Hudson River by temporarily shutting down a stretch of the Delaware Aqueduct, which supplies about half of the city’s water. The shutdown, set to begin this week and last through the winter, is part of a long-planned initiative to tackle the significant water loss from the aqueduct.

City officials have been preparing for the shutdown for years, gradually increasing water capacity from other parts of the city’s extensive 19-reservoir system to ensure uninterrupted water supply to residents. Although water will continue to flow from faucets during the shutdown, the alteration in water sources might slightly affect its renowned crisp taste.

The Delaware Aqueduct, spanning 85 miles from the Catskill region to the city’s northern suburbs, has been in operation since 1944, providing approximately half of the daily water consumption for more than 8 million New Yorkers. Despite its significance, the aqueduct has been plagued by leaks of up to 35 million gallons per day, mainly from a section beneath the Hudson River.

To address the persistent leaks, a 2.5-mile bypass tunnel was constructed under the river over the past decade. The connection of this new tunnel during the shutdown, expected to last up to eight months, will facilitate the much-needed repairs. Although over 40 miles of the aqueduct will be offline during this period, the city has made arrangements to bolster supply from alternative sources such as the Catskill Aqueduct and reservoirs in the Croton Watershed.

City officials have reassured residents that while there may be a subtle difference in taste or aroma during the repairs due to the shifting water sources, these changes do not indicate issues with the water quality. With careful planning to avoid peak summer demand, the city aims to minimise disruptions and ensure a continued water supply throughout the repair process.

As part of ongoing efforts to enhance the water system’s resilience, repairs to other sections of the aqueduct are also planned in the coming months. By diversifying water sources and implementing improvements to the ageing infrastructure, New York City remains committed to providing its residents with safe and reliable drinking water, even amid substantial repair projects like the current aqueduct shutdown.